ETB has taken into its stable experienced substation construction specialists with over 35 high voltage substations constructed and 20 years’ experience as Substations Supervisors and Foremen.
- Earth Mat Installation and Braising
- Steel works and steel erection
- Equipment Installation
- Stringing of Conductors
- Cabling and control panels
- Setting of isolators, earth switches and pantographs
- Transformer Dressing
- Yard lighting Installation
Our substations erection experts have successfully executed the below listed substations under Consolidated Power Projects (CONCO) in Botswana and around Africa
- 2002 : Segoditshane 220 kV Sub-Station Expansion Project.
- 2002 : Donga 220/132 kV Sub-Station Expansion Project.
- 2003 : Francistown West Sub-Station Project 132/11kV (New Substation)
- 2003 : Mmakgodumo Sub-Station Project 132/33kV (New Substation)
- 2003 : Orapa Slurry Dam Booster Substation 66/11kV (New Substation)
- 2004 : Ghanzi Sub-station 132/11kV (New Project)
- 2004 : Sekgoma Sub-Station 66/11kV
- 2005 : Lotsane Sub-Station 66/33kV
- 2005 : Morupule Sub-Station 220/66kV
- 2006 : Molopolole Sub-Station 33/11kV
- 2007 : Dukwi Sub-Station 132/11kV
- 2007 : Mowana Mine 132/11kV (New Project)
- 2008 : Tati Nickel Sub-Station 66/11kV
- 2008 : Hydromat Sub-Station 220/132/66kV (New Project)
- 2009 : Phakalane Sub-Station 132/11kV
- 2009 : Airport Sub-Station 132/11kV
- 2009 : Lobatse Woodhall Sub-Station 132/11kV (New Project)
- 2010 : Morupule Ventilation 66/11kV
- 2011 : Karowe Sub-Station 66/11kV (New Project)
- 2012 : Jwaneng Capacitor Bank 11kV
- 2012 : Mpanga Sub-Station 132/11kV – Uganda
- 2012 : Kamoenge Sub-Station 132/11kV – Uganda
- 2013 : Volter Sub-Station 220/132kV – Ghana
- 2014 : Cookhouse Wind Farm 70MW – South Africa
- 2014 : Usap Mine Sub-Station 132/11kV- Namibia
- 2014 : Mowana Mine Sub-Station 33kV- Zambia
- 2014 : Mobile Sub-Station 33kV
- 2015 : Orapa Feeder Bay 220/11kV
- 2016 : Debswana Letlhakane Feeder 66/11kV
- 2016 : Letlhakane Sub-Station 66/6.6kV